bath house start

Once the inaugural session of camp ended, which utilized temporary bath and kitchen facilities, Andrew got to work finalizing the design (link below) and permitting of the permanent bath house. Once we were given the green light from the county, we got to work using the same local excavator that completedĀ an extensive amount of brush clearing on the CRB site. Cody Ralston made quick work of digging and installing the perimeter drain, so we could begin form construction and plumbing. Cox Plumbing, of Waynesboro, was on hand to complete the below-slab drain pipe installation and our favorite concrete man Steve Sweet, of Lexington, followed close behind to place and finish the new slab.

PDF of bath house schematic design plan

 

 